Projects — TIB Project Information
TIB Project Information
City of Medical Lake's 2024 Scrub and Chip Seal - Red Town
2-E-897(008)-1
2-E-897(008)-1
2024 Scrub and Chip Seal - Red Town
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $752,131
County: Spokane | Legislative District: 6 | Project Length: 10.30 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/30/2024
Project Information
| Lead Agency | MEDICAL LAKE |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 6 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 10.30 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Scott Duncan |
| Contact Email | sduncan@medical-lake.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 12/30/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/15/2024 | 01/25/2024 |
| Bid Auth. Approval | 03/01/2024 | 07/03/2024 |
| Construction Approval | 03/15/2024 | 07/03/2024 |
| Project Closeout | 12/31/2024 | 12/19/2024 |
| Audit Date | 05/22/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 6,888 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 6,888 | 0 |
| Construction Engineering | 5,748 | 800 |
| Construction Contract | 689,493 | 790,331 |
| Other Construction | 0 | 757 |
| Total Construction | 695,241 | 791,888 |
| Funding Increase | 200,000 | |
| Funding Surplus | - 149,998 | |
| Total TIB Funding | 752,131 | 791,888 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MEDICAL LAKE | 39,757 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 39,757 | 5.0% |
Project Description
Scrub seal and chip seal select streets on the network.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||