Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

Town of Cusick's River Road Erosion Control

2-E-888(003)-1

2-E-888(003)-1
River Road Erosion Control

Eagle's Landing Resort Vicinity

FY 2025 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $50,000

County: Pend Oreille   |   Legislative District: 7   |   Project Length: 200.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency CUSICK
Funding Year 2025
Program SCPP
Current Phase Bid Authorization
Legislative District 7
Congressional District 5
Federal Route Number 9999
Project Length 200.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Everett Alford
Contact Email clerk@townofcusick.com
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   05/15/2024
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/20/2024 05/23/2024
Bid Auth. Approval 05/20/2024 05/23/2024
Construction Approval 10/30/2024
Project Closeout 02/15/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 10,000 10,000
Right of Way 0 0
Total Design 10,000 10,000
     
Construction Engineering 0 0
Construction Contract 40,000 40,000
Other Construction 0 0
Total Construction 40,000 40,000
     
Total TIB Funding 50,000 50,000

Local Funding Partners

Funding Amount Percent
CUSICK 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Pend Oreille River is migrating and embankment erosion threatens the shared use path and roadway.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.