Two areas of river embankment have scoured with past high river levels. This dropoff is currently at edge of pavement (edge of path - which is a managed shoulder bike lane) but some parts of the pavement have fallen. Currently the path (shoulder managed lane) is closed with temporary traffic control devices. River levels flucuate with dam operations. Currently the dam gates are inoperable and may present an opportunity for the work to occur this year while river levels are low. TIB staff performed a field visit in late April, TIB does have concerns the pathway may not survive through next year and that erosion is likely to continue and threaten the roadway in future years if not managed.
Projects — TIB Project Information
TIB Project Information
Town of Cusick's River Road Erosion Control
2-E-888(003)-1
2-E-888(003)-1
River Road Erosion Control
Eagle's Landing Resort Vicinity
FY 2025 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $50,000
County: Pend Oreille | Legislative District: 7 | Project Length: 200.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | CUSICK |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Bid Authorization |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 200.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Everett Alford |
Contact Email | clerk@townofcusick.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/15/2024 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/20/2024 | 05/23/2024 |
Bid Auth. Approval | 05/20/2024 | 05/23/2024 |
Construction Approval | 10/30/2024 | |
Project Closeout | 02/15/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,000 | 10,000 |
Right of Way | 0 | 0 |
Total Design | 10,000 | 10,000 |
Construction Engineering | 0 | 0 |
Construction Contract | 40,000 | 40,000 |
Other Construction | 0 | 0 |
Total Construction | 40,000 | 40,000 |
Total TIB Funding | 50,000 | 50,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CUSICK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Pend Oreille River is migrating and embankment erosion threatens the shared use path and roadway.
Existing Condition
Project Benefits
- Preserve and protect shared use path and roadway from Pend Oreille River embankment erosion. This effort is a temporary embankment protection project to buy time for a more perminant fix yet to be scoped.
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |