Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Tonasket's 2024 Street Maintenance

2-E-885(004)-1

2-E-885(004)-1
2024 Street Maintenance

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $282,896

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/14/2024

Project Information

Lead Agency TONASKET
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Alice Attwood
Contact Email clerktreasurer@tonasketwa.gov
TIB Engineer Andrew Beagle
Last Payment Date 11/14/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/16/2024
Bid Auth. Approval 04/15/2024 01/16/2024
Construction Approval 06/30/2024 07/11/2024
Project Closeout 10/30/2024 10/31/2024
Audit Date   11/14/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 308,051 282,896
Other Construction 0 0
Total Construction 308,051 282,896
     
Funding Surplus - 25,155  
Total TIB Funding 282,896 282,896

Local Funding Partners

Funding Amount Percent
TONASKET 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Clean and Seal road surface cracking on segments throughout Tonasket.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments