City of Okanogan's 2023 Maintenance Project

2-E-881(006)-1

2-E-881(006)-1
2023 Maintenance Project

Citywide

FY 2024 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $242,970

County: Okanogan   |   Legislative District: 7   |   Project Length: 16.20   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 12/02/2024

Project Information

Lead Agency OKANOGAN
Funding Year 2024
Program SCPP
Current Phase Closeout
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 16.20 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Shawn Davisson
Contact Email publicworks@okanogancity.com
TIB Engineer Andrew Beagle
Last Payment Date 12/02/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/30/2023
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/17/2023 04/20/2023
Bid Auth. Approval 05/01/2023 06/06/2023
Construction Approval 06/30/2023 07/20/2023
Project Closeout 11/30/2024 11/20/2024
Audit Date   12/02/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 9,808 10,250
Right of Way 0 0
Total Design 9,808 10,250
     
Construction Engineering 29,423 47,116
Construction Contract 176,838 198,392
Other Construction 0 0
Total Construction 206,261 245,508
     
Funding Increase 42,086  
Funding Surplus - 15,185  
Total TIB Funding 242,970 255,758

Local Funding Partners

Funding Amount Percent
OKANOGAN 12,788 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 12,788 5.0%

Project Description

Crack Seal and Pavement Repair throughout the city.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.