Town of Coulee Dam's 2024 Street Maintenance
2-E-878(007)-1
2-E-878(007)-1
2024 Street Maintenance
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $159,026
County: Okanogan/Douglas/Grant | Legislative District: 7 | Project Length: 3.71 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/14/2024
Project Information
| Lead Agency | COULEE DAM |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 3.71 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Stephani Bowden |
| Contact Email | cdclerk@couleedam.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 11/14/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 06/25/2024 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 06/28/2024 | 06/28/2024 |
| Bid Auth. Approval | 06/28/2024 | 06/28/2024 |
| Construction Approval | 06/28/2024 | 06/28/2024 |
| Project Closeout | 10/31/2024 | 11/06/2024 |
| Audit Date | 11/14/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 135,262 | 159,026 |
| Other Construction | 28,016 | 0 |
| Total Construction | 163,278 | 159,026 |
| Funding Surplus | - 4,252 | |
| Total TIB Funding | 159,026 | 159,026 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| COULEE DAM | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Citywide maintenance and chip seal prep work. TERO fees associated with this work and companion 2024 Chip Seal Project.
Existing Condition
Project Benefits
- Address maintenance needs ahead of chip seal.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||