TIB Project Information

Town of Wilbur's 2024 Street Maintenance

2-E-875(007)-1

2-E-875(007)-1
2024 Street Maintenance

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $31,476

County: Lincoln   |   Legislative District: 9   |   Project Length: 0.00   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency WILBUR
Funding Year 2025
Program SCPP
Current Phase Bid Authorization
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Melissa Bulger
Contact Email tow@wilburwa.com
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 12/21/2023
Bid Auth. Approval 06/01/2024 12/21/2023
Construction Approval 01/20/2025
Project Closeout 10/01/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 31,476 31,476
Other Construction 0 0
Total Construction 31,476 31,476
     
Total TIB Funding 31,476 31,476

Local Funding Partners

Funding Amount Percent
WILBUR 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Crack Sealing, 1/4 cracks, Mastic repair for wider cracks, Pavement repair for potholes

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.