Many streets are in need of crack sealing to prevent further deterioration
Projects — TIB Project Information
TIB Project Information
Town of Wilbur's 2024 Street Maintenance
2-E-875(007)-1
2-E-875(007)-1
2024 Street Maintenance
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $53,736
County: Lincoln | Legislative District: 9 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | WILBUR |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Melissa Bulger |
| Contact Email | tow@wilburwa.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 12/21/2023 |
| Bid Auth. Approval | 05/01/2025 | 05/19/2025 |
| Construction Approval | 06/01/2025 | 06/30/2025 |
| Project Closeout | 10/30/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 31,476 | 53,736 |
| Other Construction | 0 | 0 |
| Total Construction | 31,476 | 53,736 |
| Funding Increase | 22,260 | |
| Total TIB Funding | 53,736 | 53,736 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WILBUR | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Crack Sealing, 1/4 cracks, Mastic repair for wider cracks, Pavement repair for potholes
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||