High percentage of gravel streets on city network.
Projects — TIB Project Information
TIB Project Information
Town of Reardan's Gravel Street Otta Seal
2-E-873(007)-1
2-E-873(007)-1
Gravel Street Otta Seal
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $709,373
County: Lincoln | Legislative District: 9 | Project Length: 3.40 | TIB Engineer: Andrew Beagle | Last Payment Date: 09/27/2024
Project Information
Lead Agency | REARDAN |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 9, 5 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 3.40 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Sandra Matis |
Contact Email | clerk@townofreardan.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 09/27/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/09/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 10/20/2023 | 10/20/2023 |
Bid Auth. Approval | 03/01/2024 | 04/08/2024 |
Construction Approval | 04/21/2024 | 05/30/2024 |
Project Closeout | 12/15/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 25,000 | 25,000 |
Right of Way | 0 | 0 |
Total Design | 25,000 | 25,000 |
Construction Engineering | 50,000 | 50,000 |
Construction Contract | 775,000 | 529,773 |
Other Construction | 0 | 104,600 |
Total Construction | 825,000 | 684,373 |
Funding Surplus | - 140,627 | |
Total TIB Funding | 709,373 | 709,373 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
REARDAN | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Convert all gravel streets to surfaced street using otta seal treatment.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |