City of Davenport's 2022 Seal Coat Award
2-E-870(005)-1
2-E-870(005)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $226,241
County: Lincoln | Legislative District: 13 | Project Length: 0.75 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/14/2024
Project Information
Lead Agency | DAVENPORT |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.75 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Steve Goemmel |
Contact Email | sgoemmel@davenportwa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/14/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/13/2023 |
Bid Auth. Approval | 05/01/2023 | 08/09/2023 |
Construction Approval | 08/22/2023 | 06/25/2024 |
Project Closeout | 10/31/2024 | 11/04/2024 |
Audit Date | 11/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 22,000 | 13,205 |
Right of Way | 0 | 0 |
Total Design | 22,000 | 13,205 |
Construction Engineering | 22,000 | 7,160 |
Construction Contract | 192,200 | 205,876 |
Other Construction | 0 | 0 |
Total Construction | 214,200 | 213,036 |
Funding Increase | 7,136 | |
Funding Surplus | - 17,095 | |
Total TIB Funding | 226,241 | 226,241 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
DAVENPORT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Scrub and Fog Seal of the following segments Adams Street - 12th St to 7th St 10th Street - Morgan St to Jefferson St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |