Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Soap Lake's 2024 Scrub Seal - Red Town Initative

2-E-865(011)-1

2-E-865(011)-1
2024 Scrub Seal - Red Town Initative

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $1,190,400

County: Grant   |   Legislative District: 12   |   Project Length: 6.69   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 09/26/2024

Project Information

Lead Agency SOAP LAKE
Funding Year 2024
Program SCPP
Current Phase Construction
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 6.69 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Brooky Olson
Contact Email brookyo@soaplakewa.gov
TIB Engineer Andrew Beagle
Last Payment Date 09/26/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   10/30/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 11/08/2023 11/16/2023
Bid Auth. Approval 03/01/2024 04/15/2024
Construction Approval 05/01/2024 05/21/2024
Project Closeout 10/25/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,000 25,000
Right of Way 0 0
Total Design 25,000 25,000
     
Construction Engineering 202,100 173,400
Construction Contract 1,922,900 992,000
Other Construction 0 0
Total Construction 2,125,000 1,165,400
     
Funding Surplus - 959,600  
Total TIB Funding 1,190,400 1,190,400

Local Funding Partners

Funding Amount Percent
SOAP LAKE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Scrub and fog seal treatements.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments