Projects — TIB Project Information
TIB Project Information
City of Royal City's 2022 Overlay Award
2-E-864(007)-1
2-E-864(007)-1
2022 Overlay Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $428,669
County: Grant | Legislative District: 13 | Project Length: 1.21 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/29/2025
Project Information
| Lead Agency | ROYAL CITY |
| Funding Year | 2024 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 1.21 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | John Lasen |
| Contact Email | rcpw@royalcitywa.org |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 01/29/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/02/2022 | |
| Delayed Project Date | 07/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2023 | 12/21/2022 |
| Bid Auth. Approval | 05/15/2024 | 06/26/2024 |
| Construction Approval | 08/15/2024 | 08/07/2024 |
| Project Closeout | 12/31/2024 | 01/23/2025 |
| Audit Date | 01/29/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 63,650 | 45,000 |
| Right of Way | 0 | 0 |
| Total Design | 63,650 | 45,000 |
| Construction Engineering | 63,650 | 45,401 |
| Construction Contract | 551,475 | 360,830 |
| Other Construction | 0 | 0 |
| Total Construction | 615,125 | 406,231 |
| Funding Surplus | - 250,106 | |
| Total TIB Funding | 428,669 | 451,231 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROYAL CITY | 22,562 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 22,562 | 5.0% |
Project Description
Calla Loop - Hawthorne Ave to Hawthorne Ave Grape Street - Hemlock Ave to Hawthorne Ave Hawthorne Avenue - Balsam St to Grape St Hemlock Avenue - Balsam St to Grape St Calla Street - Hemlock Ave to Hawthorne Ave Balsam St - Hemlock Ave to Hawthorne Ave
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||