Projects — TIB Project Information
TIB Project Information
Town of Mattawa's 2025 Red Town Initiative
2-E-862(011)-1
2-E-862(011)-1
2025 Red Town Initiative
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $1,082,101
County: Grant | Legislative District: 13 | Project Length: 5.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/27/2025
Project Information
| Lead Agency | MATTAWA |
| Funding Year | 2026 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 5.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Juan Ledezma |
| Contact Email | jledezma@cityofmattawa-wa.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 10/27/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 09/27/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 11/01/2024 | 10/22/2024 |
| Bid Auth. Approval | 03/01/2025 | 04/08/2025 |
| Construction Approval | 04/22/2025 | 05/02/2025 |
| Project Closeout | 10/31/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 88,136 | 87,500 |
| Right of Way | 0 | 0 |
| Total Design | 88,136 | 87,500 |
| Construction Engineering | 110,169 | 82,500 |
| Construction Contract | 1,101,695 | 912,101 |
| Other Construction | 0 | 0 |
| Total Construction | 1,211,864 | 994,601 |
| Funding Surplus | - 217,899 | |
| Total TIB Funding | 1,082,101 | 1,082,101 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MATTAWA | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Pulverize and double chip seal
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||