Projects — TIB Project Information
TIB Project Information
City of Grand Coulee's 2022 Crack Seal
2-E-859(007)-1
2-E-859(007)-1
2022 Crack Seal
Citywide
FY 2024 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $191,553
County: Grant | Legislative District: 7 | Project Length: 1.50 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/02/2024
Project Information
Lead Agency | GRAND COULEE |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Closeout |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 1.50 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dennis Francis |
Contact Email | shopboss@gccitywa.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/14/2022 |
Bid Auth. Approval | 03/15/2023 | 05/28/2024 |
Construction Approval | 06/15/2024 | 06/28/2024 |
Project Closeout | 10/31/2024 | 11/18/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 77,000 | 191,553 |
Other Construction | 0 | 0 |
Total Construction | 77,000 | 191,553 |
Funding Increase | 114,553 | |
Total TIB Funding | 191,553 | 191,553 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRAND COULEE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Crack Seal
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |