Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Grand Coulee's 2022 Seal Coat Award

2-E-859(006)-1

2-E-859(006)-1
2022 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $78,980

County: Grant   |   Legislative District: 12   |   Project Length: 0.43   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency GRAND COULEE
Funding Year 2024
Program SCPP
Current Phase Design
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 0.43 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dennis Francis
Contact Email shopboss@gccitywa.org
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/14/2022
Bid Auth. Approval 02/15/2024
Construction Approval 03/01/2024
Project Closeout 09/15/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 9,040 9,040
Right of Way 0 0
Total Design 9,040 9,040
     
Construction Engineering 9,040 9,040
Construction Contract 60,900 60,900
Other Construction 0 0
Total Construction 69,940 69,940
     
Total TIB Funding 78,980 78,980

Local Funding Partners

Funding Amount Percent
GRAND COULEE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip Seal of the following segments Main Street - Spokane Wy to Federal Ave Federal Avenue - Main St to Spokane Wy Federal Avenue - Spokane Wy to W Grand Coulee Ave (SR 174)

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments