 Projects — TIB Project Information

TIB Project Information

City of George's 2022 Crack Seal

2-E-858(008)-1

2-E-858(008)-1
2022 Crack Seal

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $8,518

County: Grant   |   Legislative District: 13   |   Project Length: 1.40   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency GEORGE
Funding Year 2024
Program SCPP
Current Phase Closeout
Legislative District 13
Congressional District 4
Federal Route Number 9999
Project Length 1.40 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Don Entzel
Contact Email mayor@cityofgeorge.org
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/28/2023 03/21/2023
Bid Auth. Approval 06/30/2023 03/21/2023
Construction Approval 07/31/2023 03/21/2023
Project Closeout 03/15/2024 04/12/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 20,655 8,518
Other Construction 0 0
Total Construction 20,655 8,518
     
Funding Surplus - 12,137  
Total TIB Funding 8,518 8,518

Local Funding Partners

Funding Amount Percent
GEORGE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Crack seal of multiple streets within City Limits.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.