Town of Electric City's 2022 Seal Coat Award
2-E-857(005)-1
2-E-857(005)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $483,522
County: Grant | Legislative District: 12 | Project Length: 2.51 | TIB Engineer: Andrew Beagle | Last Payment Date: 12/02/2024
Project Information
Lead Agency | ELECTRIC CITY |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Closeout |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 2.51 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Diane Kohout |
Contact Email | mayor@electriccity.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 05/01/2023 | 04/26/2023 |
Bid Auth. Approval | 03/15/2024 | 05/28/2024 |
Construction Approval | 06/15/2024 | 06/28/2024 |
Project Closeout | 10/31/2024 | 11/22/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,936 | 14,031 |
Right of Way | 0 | 0 |
Total Design | 23,936 | 14,031 |
Construction Engineering | 23,936 | 16,700 |
Construction Contract | 287,182 | 452,552 |
Other Construction | 0 | 239 |
Total Construction | 311,118 | 469,491 |
Funding Increase | 176,795 | |
Funding Surplus | - 28,327 | |
Total TIB Funding | 483,522 | 483,522 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ELECTRIC CITY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Double Chip and fog seal of the road. City prep work and County chip/fog seal of the following segments Linda - end to end Electric Boulevard - Electric Place to SR 155 Electric Place - End to End Gold Avenue - End to End McNett Avenue - Park Ave to Electric Pl Sunset Drive - End to End Washington Place - Park Ave to Electric Pl Western Avenue - McNett Ave to Sunset Drive Snyder Hill Road - End to End
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |