Town of Electric City's 2022 Seal Coat Award

2-E-857(005)-1

2-E-857(005)-1
2022 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $335,054

County: Grant   |   Legislative District: 12   |   Project Length: 2.51   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency ELECTRIC CITY
Funding Year 2024
Program SCPP
Current Phase Design
Legislative District 12
Congressional District 4
Federal Route Number 9999
Project Length 2.51 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Diane Kohout
Contact Email mayor@electriccity.us
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 05/01/2023 04/26/2023
Bid Auth. Approval 03/15/2024
Construction Approval 04/01/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 23,936 23,936
Right of Way 0 0
Total Design 23,936 23,936
     
Construction Engineering 23,936 23,936
Construction Contract 287,182 287,182
Other Construction 0 0
Total Construction 311,118 311,118
     
Total TIB Funding 335,054 335,054

Local Funding Partners

Funding Amount Percent
ELECTRIC CITY 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Double Chip and fog seal of the road. City prep work and County chip/fog seal of the following segments Linda - end to end Electric Boulevard - Electric Place to SR 155 Electric Place - End to End Gold Avenue - End to End McNett Avenue - Park Ave to Electric Pl Sunset Drive - End to End Washington Place - Park Ave to Electric Pl Western Avenue - McNett Ave to Sunset Drive Snyder Hill Road - End to End

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments