Red Town Initiative - top 5 worst pavement ratings statewide.
Projects — TIB Project Information
TIB Project Information
City of Leavenworth's 2024 Scrub Seal - Red Town InitiativeIncre
2-E-850(005)-1
2-E-850(005)-1
2024 Scrub Seal - Red Town InitiativeIncre
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $1,170,921
County: Chelan | Legislative District: 12 | Project Length: 8.02 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/18/2024
Project Information
Lead Agency | LEAVENWORTH |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 8.02 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Andi Zontek-Backstrum |
Contact Email | azontek@cityofleavenworth.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/18/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/06/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 11/05/2023 | 11/02/2023 |
Bid Auth. Approval | 02/26/2024 | 03/18/2024 |
Construction Approval | 04/03/2024 | 05/30/2024 |
Project Closeout | 10/25/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 22,500 | 25,000 |
Right of Way | 0 | 0 |
Total Design | 22,500 | 25,000 |
Construction Engineering | 140,850 | 150,000 |
Construction Contract | 1,411,650 | 1,126,023 |
Other Construction | 0 | 0 |
Total Construction | 1,552,500 | 1,276,023 |
Funding Surplus | - 404,079 | |
Total TIB Funding | 1,170,921 | 1,301,023 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LEAVENWORTH | 130,102 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 130,102 | 10.0% |
Project Description
Scrub Seal and Fog Seal multiple city streets.
Existing Condition
Project Benefits
- Increase average network PCR
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |