Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Ritzville's 2024 Street Maintenance

2-E-845(009)-1

2-E-845(009)-1
2024 Street Maintenance

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $42,312

County: Adams   |   Legislative District: 9   |   Project Length: 0.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency RITZVILLE
Funding Year 2025
Program SCPP
Current Phase Design
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 0.00 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Scott Yaeger
Contact Email scotty@co.adams.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/05/2024
Bid Auth. Approval 08/15/2025
Construction Approval 09/15/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 42,312 44,539
Other Construction 0 0
Total Construction 42,312 44,539
     
Total TIB Funding 42,312 44,539

Local Funding Partners

Funding Amount Percent
RITZVILLE 2,227 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,227 5.0%

Project Description

Crack sealing on several streets throughout the City.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments