Projects — TIB Project Information
TIB Project Information
Town of Hatton's 2024 Otta Seal
2-E-842(001)-1
2-E-842(001)-1
2024 Otta Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $297,745
County: Adams | Legislative District: 9 | Project Length: 1.40 | TIB Engineer: Jonathan Heusman | Last Payment Date: 02/14/2025
Project Information
| Lead Agency | HATTON |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 9 |
| Congressional District | 0 |
| Federal Route Number | 9999 |
| Project Length | 1.40 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Tyson Larson |
| Contact Email | tyson.larson@horrocks.com |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 02/14/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 10/12/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 10/20/2023 | 10/16/2023 |
| Bid Auth. Approval | 01/31/2024 | 03/11/2024 |
| Construction Approval | 04/30/2024 | 04/29/2024 |
| Project Closeout | 12/31/2024 | 02/12/2025 |
| Audit Date | 02/14/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 20,000 | 20,000 |
| Right of Way | 0 | 0 |
| Total Design | 20,000 | 20,000 |
| Construction Engineering | 20,909 | 20,000 |
| Construction Contract | 409,091 | 256,611 |
| Other Construction | 0 | 1,134 |
| Total Construction | 430,000 | 277,745 |
| Funding Increase | 8,745 | |
| Funding Surplus | - 161,000 | |
| Total TIB Funding | 297,745 | 297,745 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| HATTON | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Otta seal on existing gravel and paved roads.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||