Region: Northwest | Legislative District: 39 | Length: 0.21 mi. | FY 2026 Urban Arterial Program (UAP) |
![]() |
Existing ConditionsThe Jones/John Liner/Trail Road Corridor Project is a multi-phased project that will create an alternative east-west route to State Route (SR) 20 relieving congestion and providing capacity to accommodate current and future commercial and industrial growth. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 332,395 | 60,805 | 393,200 |
Right of Way | 59,175 | 10,825 | 70,000 |
Construction | 1,757,485 | 322,615 | 2,080,100 |
Project Totals | $2,149,055 | $394,245 | $2,543,300 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
84.5% | 15.5% | 15% |
The Jones/John Liner Railroad Undercrossing is a new road (1100 feet) across unimproved right of way. It will consist of one 11-foot travel lane in each direction, curb/gutter on both sides, a three-foot buffer strip and ten-foot multi-use path on the north side, five-foot sidewalk on the south side, redesign the drainage ditch and replace with a modern storm system, and install street lighting in key locations.