Town of Pe Ell
2025 Otta Seal
Multiple Locations
TIB Award Amount
$171,128
Region: West   |   Legislative District: 19   |   Length: 0.00 mi. FY 2026 Small City Preservation Program (SCPP)

Existing Conditions

Anticipated Project Costs

  TIB Funds Local Funds Total Costs
Design 7,412 0 7,412
Right of Way 0 0 0
Construction 163,716 0 163,716
Project Totals $171,128 $0 $171,128

Local Match

TIB Participation Local Match Minimum Local Match
100.0% 0.0% 0%

Description of Improvements

Otta seal