Region: East | Legislative District: 16 | Length: 0.00 mi. | FY 2025 Small City Preservation Program (SCPP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 23,000 | 1,210 | 24,210 |
Right of Way | 0 | 0 | 0 |
Construction | 276,597 | 14,558 | 291,155 |
Project Totals | $299,597 | $15,768 | $315,365 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
chip seal, street sweeping, vinyl stop bars, vinyl crosswalks, striping.