City of Granite Falls
2025 Crack Seal
Multiple Locations
TIB Award Amount
$62,100
Region: Puget Sound   |   Legislative District: 39   |   Length: 0.00 mi. FY 2026 Small City Maintenance Program (SCMP)

Existing Conditions

Several Streets in the City are beginning to show signs (cracks) of needing to be resurfaced soon.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 62,100 6,900 69,000
Project Totals $62,100 $6,900 $69,000

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

Perform a City-wide crack seal project. This work will be the first crack seal phase to crack seal all streets in Granite Falls that have TIB PCRs between 45 and 80.