Town of Electric City
2024 Street Maintenance
Multiple Locations
TIB Award Amount
$155,000
Region: East   |   Legislative District: 7   |   Length: 0.00 mi. FY 2025 Small City Maintenance Program (SCMP)

Existing Conditions

Pavement cracks and pavement degradation exists on many roadway areas in the City.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 155,000 0 155,000
Project Totals $155,000 $0 $155,000

Local Match

TIB Participation Local Match Minimum Local Match
100.0% 0.0% 0%

Description of Improvements

Clean and install crack sealant and dig out and repair areas.