City of Soap Lake
Daisy Street SR 17 Sidewalk Improvements Phase II
Main Ave E to 3rd Ave SE
TIB Award Amount
$76,424
Region: East   |   Legislative District: 7   |   Length: 0.18 mi. FY 2026 Small City Arterial Program (SCAP)

Existing Conditions

Non-compliant curb ramps, driveway accesses, and surface discontinuities existing which serves as obstacles for pedestrians accessing the stores, restaurants, and other businesses along this side of Daisy Street.

Project Funding

  TIB Funds Local Funds Total Costs
Design 8,654 55,446 64,100
Right of Way 0 0 0
Construction 67,771 434,229 502,000
Project Totals $76,424 $489,676 $566,100

Local Match

TIB Participation Local Match Minimum Local Match
13.5% 86.5% 0%

Description of Improvements

Phase II will construct sidewalk, compliant curb ramps, driveway accesses, remove tripping hazards, and remove other obstructions. This project will provide an ADA compliant access along the west side of Daisy Street (SR 17) from 3rd Ave SE to Main Avenue.