Region: Puget Sound | Legislative District: 31 | Length: 0.10 mi. | FY 2025 Small City Arterial Program (SCAP) |
![]() |
Existing ConditionsThe current stop conditions on Emery Avenue causes traffic is backed up on Emery causing significant delays. In addition there is a high volkume pedestrian traffic crossing from the main community (south of SR 162) to the Post Office (north of SR 162). |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 108,778 | 0 | 108,778 |
Right of Way | 0 | 0 | 0 |
Construction | 676,844 | 0 | 676,844 |
Project Totals | $785,622 | $0 | $785,622 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
This project will construct a compact roundabout at the intersection of SR 162 and Emery Avenue with pedestrian crossing improvements on the east leg.