| Region: East | Legislative District: 7 | Length: 0.13 mi. | FY 2025 Small City Arterial Program (SCAP) |
| Agency Name | City of Omak |
| Funding Year | FY 2025 |
| Program | SCAP |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | |
| Project Length | 0.13 mi. |
| ADT | 0 |
| Functional Class | |
| Type of Work | |
| Project Contact | Wayne Beetchenow |
| Contact Email | publicworks@omakcity.com |
| Milestone | Target Date |
|---|---|
| Environmental Documentation Complete & Permits Approved | |
| Right of Way Acquisition Complete | |
| Start Design Engineering | 01/01/2024 |
| Contract Advertisement | 02/01/2025 |
| Contract Award | 04/01/2025 |
| Project Closeout | 12/01/2025 |
![]() |
Existing ConditionsJonathan Avenue is partially constructed and if extended can complete a portion of the grid network and increasing multimodal access from the developing residential in North Omak. This lack of grid connectivity contributes to traffic congestion on SR 215. |
| TIB Funds | Local Funds | Total Costs | |
|---|---|---|---|
| Design | 90,820 | 4,780 | 95,600 |
| Right of Way | 4,750 | 250 | 5,000 |
| Construction | 696,730 | 36,670 | 733,400 |
| Project Totals | $792,300 | $41,700 | $834,000 |
| TIB Participation | Local Match | Minimum Local Match |
|---|---|---|
| 95.0% | 5.0% | 5% |
Extend Jonathan Avenue, constructing a new roadway connecting Quince Street to Pine Street and Oak Street. Construction will consists of 5' sidewalk, 8' parking, 11' travel lane on both sides.