City of Everson
SR 544 Sidewalk
Portions of Meade Ave and Nolte Rd
TIB Award Amount
$564,867
Region: West   |   Legislative District: 42   |   Length: 0.00 mi. FY 2026 Complete Streets Program (CSP)

Existing Conditions

The Everson Elementary School currently has no sidewalks along SR 544 going to the northeast of the school on that side of the road, and only intermittent sidewalks on the east side of SR 544. There is not a consistent linear path for pedestrians and students to the safely travel to the elementary school from other parts of town.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 564,867 2,505,071 3,069,938
Project Totals $564,867 $2,505,071 $3,069,938

Local Match

TIB Participation Local Match Minimum Local Match
18.4% 81.6% 5%

Description of Improvements

The project provides 8.0 wide sidewalks connecting downtown Everson with Everson Elementary School. Elementary Students and other pedestrians will be provided with safe and ADA compliant facilities.