City of Roslyn
2025 RRFB
Intersection of 1st St and Pennsylvania Ave
TIB Award Amount
$76,000
Region: East   |   Legislative District: 13   |   Length: 0.00 mi. FY 2026 Complete Streets Program (CSP)

Existing Conditions

1st Street (SR 903) bisects the City and serves as a barrier for access between the northeast and southwest side of the City.

Project Funding

  TIB Funds Local Funds Total Costs
Design 5,985 315 6,300
Right of Way 0 0 0
Construction 70,015 3,685 73,700
Project Totals $76,000 $4,000 $80,000

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

The project would add four rectangular-rapid-flashing-beacons (RRFBs) to the intersection of 1st Street and Pennsylvania Ave.