Region: East | Legislative District: 14 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsThe intersection of S. Toppenish Avenue and W. 1st Avenue existing sidewalks, curb ramps, and crosswalks are non-ADA compliant and do not provide a safe route for pedestrian travel. The lane widths are over 16 feet wide and not ideal for safely crossing the street. The intersections roadway surface is deteriorating asphalt. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 175,968 | 19,552 | 195,520 |
Right of Way | 0 | 0 | 0 |
Construction | 1,353,586 | 150,399 | 1,503,985 |
Project Totals | $1,529,554 | $169,951 | $1,699,505 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
90.0% | 10.0% | 10% |
The project includes roadway, sidewalks, bulb outs, curb ramps, crosswalks, signal with pedestrian push buttons, and landscaping improvements.