Region: East | Legislative District: 12 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsMinimal pavement section with travelled way and on-street parking. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 152,160 | 38,040 | 190,200 |
Right of Way | 0 | 0 | 0 |
Construction | 1,111,200 | 277,800 | 1,389,000 |
Project Totals | $1,263,360 | $315,840 | $1,579,200 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
80.0% | 20.0% | 20% |
The project consists of reconfigured roadway with one-way lane and two-way bicycle track, sidewalks, pedestrian lighting, designated parking, and safety features like RRFBs and ADA-compliant ramps.