City of Montesano
McBryde Sidewalk CSP
Satsop St to Adams St
TIB Award Amount
$235,000
Region: West   |   Legislative District: 24   |   Length: 0.00 mi. FY 2026 Complete Streets Program (CSP)

Existing Conditions

McBryde Avenue is a primary pedestrian corridor for the north side of the City. This corridor has pedestrian facilities west of Church Street to link the northwest side of town to the high school but has no facilities or inadequate facilities to serve the northeast areas of the City. The existing McBryde Avenue corridor west of Church Street is very narrow with a 10 foot asphalt lanes and limited shoulder width in many locations.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 235,000 24,000 259,000
Project Totals $235,000 $24,000 $259,000

Local Match

TIB Participation Local Match Minimum Local Match
90.7% 9.3% 5%

Description of Improvements

Continue the work that was completed with TIB funds on the west side of the corridor by installing another 830 feet of sidewalk from Satsop Street to Adams Street.