Region: East | Legislative District: 9 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsMain St (US-12) runs east to west through Pomeroy, WA. The east end of the City is not adequately served with sidewalks. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 173,025 | 0 | 173,025 |
Right of Way | 0 | 0 | 0 |
Construction | 826,675 | 0 | 826,675 |
Project Totals | $999,700 | $0 | $999,700 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
100.0% | 0.0% | 0% |
This project will effectively close a gap in the existing sidewalk infrastructure by constructing new sidewalk from 17th Street to 25th Street.