City of Issaquah
Front Street S
135 ft s/o and 200 ft n/o SE Bush St Intersection
TIB Award Amount
$316,000
Region: Puget Sound   |   Legislative District: 5   |   Length: 0.00 mi. FY 2026 Complete Streets Program (CSP)

Existing Conditions

The crosswalk at Front Street S and SE Bush Street is utilized by community members navigating from multifamily housing located west of Front St to community facilities including to the Issaquah Community Center, Clark Elementary School, Julius Boehm Pool, and the Rainier Trail on the east side of Front St. The crosswalk location is near a bus stop that serves two bus routes. The crosswalk is the only marked crossing between the signalized intersections of Sunset Way and Clark St, spaced 0.2 miles apart. Existing conditions include very high traffic volumes, especially on Front St. There is low compliance from northbound drivers for pedestrians and vehicles turning left from westbound Bush Street onto southbound Front Street including blocking of the crosswalk and intersection. The intersection reported 11 collisions in the last 5 years, the intersection will significantly benefit from a RRFB crossing based on level of pedestrian activity and lack of compliance by drivers yielding the right of way.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 316,000 79,000 395,000
Project Totals $316,000 $79,000 $395,000

Local Match

TIB Participation Local Match Minimum Local Match
80.0% 20.0% 20%

Description of Improvements

Project will shift the crossing 20 feet south to improve pedestrian visibility, now restricted by a rockery wall; install RRFB at the crossing for pedestrian safety; improve drainage and sidewalks.