Region: West | Legislative District: 49 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsThe Transportation System Plan identifies the entire corridor on the Primary Pedestrian Network and Enhanced Transit Network but most of the corridor has narrow sidewalks (less than six-feet wide) directly adjacent to traffic. There are large gaps between marked crossings and frequent driveways to businesses along the corridor. This portion of the corridor (39th Street to Discovery Trail) is also on the Citys Bike and Small Mobility Network but there are currently no easy or comfortable connection for people walking, biking or using small mobility devices along this segment. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 57,692 | 228,538 | 286,230 |
Right of Way | 0 | 0 | 0 |
Construction | 442,308 | 1,752,137 | 2,194,445 |
Project Totals | $500,000 | $1,980,675 | $2,480,675 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
20.2% | 79.8% | 20% |
The Project aims to improve pedestrian safety, bike and small mobility connectivity, and access to transit stops with crossing improvements and a new multi-use path connection.