Region: West | Legislative District: 20 | Length: 300.00 ft. | FY 2026 Urban Active Transportation Program (ATP) |
![]() |
Existing ConditionsADA ramps on Pacific Avenue and sidewalk on the north side of Beechwood Street were installed as part of a CDBG grant for low-income areas. The city installed approximately 600 feet of sidewalk on Pacific Avenue north and south of Beechwood Street in conjunction with the CDBG grant. Sidewalk to the south will be constructed as part of the future Exit 21 improvements. Therefore, a 300 foot gap in the sidewalk is located in this section. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 23,105 | 5,695 | 28,800 |
Right of Way | 0 | 0 | 0 |
Construction | 176,895 | 43,605 | 220,500 |
Project Totals | $200,000 | $49,300 | $249,300 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
80.2% | 19.8% | 15% |
Completing the sidewalk in this area will provide a safe route to connect residential area with commercial area to the north and south, as well as complete a pathway to downtown, city parks and Horseshoe Lake.