Region: Puget Sound | Legislative District: 12 | Length: 380.00 ft. | FY 2026 Urban Active Transportation Program (ATP) |
![]() |
Existing ConditionsThere is an existing gap in sidewalk between the existing Fryelands Boulevard walking trail and the concrete sidewalk on Main Street. There is also not a crosswalk between the northwest corner of the intersection and the south side of Main Street. This walking path acts as pedestrian connection to an existing coffee stand, and also provides pedestrian access to the High School. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 55,628 | 14,372 | 70,000 |
Right of Way | 0 | 0 | 0 |
Construction | 213,372 | 55,128 | 268,500 |
Project Totals | $269,000 | $69,500 | $338,500 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
79.5% | 20.5% | 20% |
This project will construct 380 linear feet of sidewalk, planter strip and curb and gutter will close the gap along Main Street. This work will also require some minor drainage modification with the construction of two catchbasins and a retaining wall approximately 5 feet in height along approximately 100 linear feet of the project.