| Region: East | Legislative District: 7 | Length: 800.00 ft. | FY 2025 Urban Active Transportation Program (ATP) |
| Agency Name | Town of Winthrop |
| Funding Year | FY 2025 |
| Program | ATP |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | |
| Project Length | 800 ft. |
| ADT | 0 |
| Functional Class | |
| Type of Work | |
| Project Contact | Jeff Sarvis |
| Contact Email | jeff@townofwinthrop.com |
| Milestone | Target Date |
|---|---|
| Start Design Engineering | 05/01/2024 |
| Contract Advertisement | 11/01/2024 |
| Contract Award | 02/15/2025 |
| Contract Completion | 10/30/2025 |
![]() |
Existing ConditionsWinthrop does not have a non-vehicular traffic network through the town. |
| TIB Funds | Local Funds | Total Costs | |
|---|---|---|---|
| Design | 69,134 | 3,639 | 72,773 |
| Right of Way | 0 | 0 | 0 |
| Construction | 459,541 | 24,186 | 483,727 |
| Project Totals | $528,675 | $27,825 | $556,500 |
| TIB Participation | Local Match | Minimum Local Match |
|---|---|---|
| 95.0% | 5.0% | 5% |
This project will connect sidewalk with two prior TIB projects, connecting sidewalks constructed on Bluff Street and Castle Ave.