City of West Richland
Keene Road Overlay
C/L to Bombing Range Rd
TIB Award Amount
$400,000
Region: Southeast   |   Legislative District: 16   |   Length: 0.00 mi. FY 2026 Arterial Preservation Program (APP)

Existing Conditions

Project Funding

  TIB Funds Local Funds Total Costs
Design 26,181 22,819 49,000
Right of Way 0 0 0
Construction 373,819 325,819 699,638
Project Totals $400,000 $348,638 $748,638

Local Match

TIB Participation Local Match Minimum Local Match
53.4% 46.6% 15%

Description of Improvements

2-inch grind and overlay, paint line