Region: Puget Sound | Legislative District: 28 | Length: 0.00 mi. | FY 2025 Arterial Preservation Program (APP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 97,434 | 17,913 | 115,347 |
Right of Way | 0 | 0 | 0 |
Construction | 579,975 | 106,630 | 686,605 |
Project Totals | $677,409 | $124,543 | $801,952 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
84.5% | 15.5% | 15% |
Grind and 2-inch overlay ofClaremont Street - Alameda Ave and 67th Ave W with 8 ADA ramps.