Region: Southwest | Legislative District: 18 | Length: 0.00 mi. | FY 2025 Arterial Preservation Program (APP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 487,448 | 121,862 | 609,310 |
Project Totals | $487,448 | $121,862 | $609,310 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
80.0% | 20.0% | 20% |
2 inch grind and overlay using waste plastic additive. WSU will assist in the specifications, inspections, and research.