| Region: Southeast | Legislative District: 16 | Length: 0.00 mi. | FY 2025 Arterial Preservation Program (APP) |
| Agency Name | City of Walla Walla |
| Funding Year | FY 2025 |
| Program | APP |
| Legislative District | 16 |
| Congressional District | 5 |
| Federal Route Number | |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | |
| Type of Work | |
| Project Contact | Monte Puymon PE |
| Contact Email | mpuymon@wallawallawa.gov |
| Milestone | Target Date |
|---|---|
| Start Design Engineering | 12/01/2023 |
| Contract Advertisement | 04/02/2024 |
| Contract Award | 05/22/2024 |
| Project Complete | 11/01/2025 |
![]() |
Existing Conditions |
| TIB Funds | Local Funds | Total Costs | |
|---|---|---|---|
| Design | 44,888 | 90,112 | 135,000 |
| Right of Way | 0 | 0 | 0 |
| Construction | 355,112 | 712,888 | 1,068,000 |
| Project Totals | $400,000 | $803,000 | $1,203,000 |
| TIB Participation | Local Match | Minimum Local Match |
|---|---|---|
| 33.3% | 66.7% | 20% |
2 inch grind and inlay, crack seal and minor pavement repair. Replace non compliant ADA ramps.