Region: Southeast | Legislative District: 16 | Length: 0.00 mi. | FY 2025 Arterial Preservation Program (APP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 44,888 | 90,112 | 135,000 |
Right of Way | 0 | 0 | 0 |
Construction | 355,112 | 712,888 | 1,068,000 |
Project Totals | $400,000 | $803,000 | $1,203,000 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
33.3% | 66.7% | 20% |
2 inch grind and inlay, crack seal and minor pavement repair. Replace non compliant ADA ramps.