Bill # |
Payment Date |
Type |
Predesign |
Spec. Study |
DE Engr. |
Right of Way |
CN Engr. |
CN Other |
CN Contract |
Total |
1 |
01/02/2014 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
14,618.88 |
14,618.88 |
2 |
05/01/2014 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
9,770.09 |
9,770.09 |
3 |
07/14/2014 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
55,335.04 |
55,335.04 |
4 |
07/29/2014 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
107,681.54 |
107,681.54 |
5 |
08/19/2014 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
17,296.65 |
17,296.65 |
6 |
12/29/2014 |
Audit |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
10,773.80 |
10,773.80 |
TOTAL PAYMENTS |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
215,476.00 |
215,476.00 |