Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 08/14/2024 Payment 0.00 0.00 0.00 0.00 949.89 4,428.18 14,467.49 19,845.56
2 09/27/2024 Payment 0.00 0.00 0.00 0.00 48,387.48 0.00 0.00 48,387.48
3 12/30/2024 Audit 0.00 0.00 0.00 0.00 -48,387.48 32,240.50 29,674.94 13,527.96
TOTAL PAYMENTS 0.00 0.00 0.00 0.00 949.89 36,668.68 44,142.43 81,761.00