Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 03/29/2012 Payment 0.00 0.00 1,835.10 0.00 0.00 0.00 0.00 1,835.10
2 05/01/2012 Payment 0.00 0.00 1,162.60 0.00 0.00 0.00 0.00 1,162.60
3 08/01/2012 Payment 0.00 0.00 5,486.81 0.00 0.00 0.00 0.00 5,486.81
4 08/02/2012 Payment 0.00 0.00 0.00 0.00 0.00 0.00 40,451.89 40,451.89
5 09/14/2012 Audit 0.00 0.00 -3,872.51 0.00 4,900.00 0.00 3,228.11 4,255.60
TOTAL PAYMENTS 0.00 0.00 4,612.00 0.00 4,900.00 0.00 43,680.00 53,192.00