Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 06/15/2009 Payment 0.00 0.00 0.00 0.00 0.00 0.00 1,955.06 1,955.06
2 08/27/2009 Payment 0.00 0.00 0.00 0.00 0.00 0.00 15,354.07 15,354.07
3 10/20/2009 Payment 0.00 0.00 0.00 0.00 0.00 0.00 772.02 772.02
TOTAL PAYMENTS 0.00 0.00 0.00 0.00 0.00 0.00 18,081.15 18,081.15