Bill # |
Payment Date |
Type |
Predesign |
Spec. Study |
DE Engr. |
Right of Way |
CN Engr. |
CN Other |
CN Contract |
Total |
1 |
09/18/2009 |
Payment |
0.00 |
0.00 |
16,000.00 |
0.00 |
0.00 |
0.00 |
0.00 |
16,000.00 |
2 |
10/26/2009 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
105,288.80 |
105,288.80 |
3 |
12/10/2009 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
57,145.88 |
1,061.05 |
0.00 |
58,206.93 |
3 |
12/15/2009 |
Payment |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
179,164.65 |
179,164.65 |
4 |
04/13/2010 |
Payment |
0.00 |
0.00 |
-900.48 |
0.00 |
-3,216.17 |
-59.72 |
-35,880.01 |
-40,056.38 |
TOTAL PAYMENTS |
0.00 |
0.00 |
15,099.52 |
0.00 |
53,929.71 |
1,001.33 |
248,573.44 |
318,604.00 |