FY 2027 CSP Selections

City of Tacoma
S Park Avenue Greenway
S 86th St to S 76th St
TIB Award Amount
$478,745
Region: Puget Sound   |   Legislative District: 29   |   Length: 0.65 mi. FY 2027 Complete Streets Program (CSP)

Project Information

Agency Name City of Tacoma
Funding Year FY 2027
Program CSP
Legislative District 29
Congressional District 10
Federal Route Number 9999
Project Length 0.65 mi.
ADT 1,598
Functional Class
Type of Work Pedestrian
Project Contact Dan Hansen
Contact Email dhansen1@tacoma.gov

Project Schedule

Milestone Target Date
Start Design Engineering 02/01/2026
Contract Advertisement 12/14/2026
Contract Award 01/10/2027
Contract Completion 07/02/2027

Existing Conditions

S Park Ave in Tacomas Fern Hill Neighborhood faces substantial traffic challenges that compromise safety and livability in the area. Despite being a local access street and designated a neighborhood greenway in the Citys Transportation Master Plan, S Park Ave attracts significant cut-through traffic avoiding the parallel arterial, Yakima Ave. Traffic counts from 2021-2025 range from 1,552 to 1,936 vehicles, excessively high for a neighborhood street. 85th percentile speeds have reached 32.5 mph, well above the posted 20 mph limit. The corridor is a key walking route to Fern Hill Elementary and runs through the Fern Hill Neighborhood Business District, serving as a significant route for pedestrians and cyclists. In the past three years, four pedestrian or cyclist collisions and many other injury crashes have occurred on S Park Ave. The data, along with extensive feedback from residents, parents and the school district underscore the need for traffic calming and safety improvements.

Project Funding

  TIB Funds Local Funds Total Costs
Design 33,954 8,488 42,442
Right of Way 0 0 0
Construction 444,792 111,198 555,990
Project Totals $478,745 $119,687 $598,432

Local Match

TIB Participation Local Match Minimum Local Match
80.0% 20.0% 20%

Description of Improvements

The project includes curb bulbs and a raised school crosswalk at 86th, 4 speed humps, a traffic circle, a traffic diverter, and approximately 160 ft of new sidewalk to eliminate an existing gap.