Region: Northeast | Legislative District: 12 | Length: 0.35 mi. | FY 2025 Urban Arterial Program (UAP) |
![]() |
Existing Conditions9th Street is a minor arterial supporting freight connections. The street has four lanes and there are no exclusive left-turn lanes in the corridor. From 1/1/2020 to 12/31/2022 there were 69 crashes, 66 took place at intersections and 21 were injury crashes. The route is prioritized in the 2022 Wenatchee Valley Bicycle Master Plan and destinations identified in the 2018 Human Services Transportation Plan. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 141,792 | 35,498 | 177,290 |
Right of Way | 17,403 | 4,357 | 21,760 |
Construction | 1,039,805 | 260,315 | 1,300,120 |
Project Totals | $1,199,000 | $300,170 | $1,499,170 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
80.0% | 20.0% | 20% |
Reconfigure from four to three traffic lane conversion, bike lanes and signal modifications.