City of Bremerton
Washington Avenue / 11th Street
Pacific Ave to Manette Bridge
TIB Award Amount
$1,742,143
Region: Northwest   |   Legislative District: 23   |   Length: 0.27 mi. FY 2023 Urban Arterial Program (UAP)

Existing Conditions

The project is needed to provide sustainable, efficient, and safe travel for people who use the Washington Boulevard corridor. The Washington and Manette Bridge intersection is signalized and currently operates at a Level of Service (LOS) E with 740 foot queues. The project segment from Pacific Avenue to the Manette Bridge does not provide safe, ADA accessible bicycle and pedestrian infrastructure that supports the City's plans for improving active transportation modes of travel. Some areas along the existing northeast side of the corridor include only a 2 foot wide sidwalk that doesn't provide ADA accessibility. There is a need to improve the long term functionality of the Washington Boulevard/Mannette Bridge intersection and a need to provide safe, ADA accessible, connected pedestrian pathways.

Project Funding

  TIB Funds Local Funds Total Costs
Design 0 0 0
Right of Way 0 0 0
Construction 1,742,143 4,264,600 6,006,743
Project Totals $1,742,143 $4,264,600 $6,006,743

Local Match

TIB Participation Local Match Minimum Local Match
29.0% 71.0% 20%

Description of Improvements

The project will replace the signalized intersection of Washington Avenue and Manette Bridge with a roundabout. The project will reconstruct Washington/11th from Pacific Avenue to Manette Bridge and provide ADA accessible sidewalks, bike lanes, lighting, stormwater improvements, and other traffic calming design features.